Page 5 - SRNS Today January 2022
P. 5

JANUARY 2022    |   SRNS TODAY   |   5

        SRS Tritium projects complete banner year



         T      o continue successfully serving the NNSA missions at SRS,   will eliminate the lab’s reliance on aging ventilation associated with
                SRNS is carrying out a number of construction projects.
                                                                HAOM. The first phase focused on a new 100-foot exhaust stack. In
                Much has been said about the large NNSA capital projects
                                                                three separate sections, the early work included clearing and grading
        currently underway; however, there are numerous lesser-known SRNS   addition to assembling and erecting the stack itself, which came in
        construction projects that are also vital to ensuring that SRS is able   the area, installing a new road, and removing existing overhead power
        to continue fulfilling these important national needs, especially in the   lines and a power pole. The remaining work, which includes ductwork,
        Savannah River Tritium Enterprise (SRTE).               fans, an electrical building, and an emergency diesel generator, is
                                                                scheduled to complete during 2022.
        “We refer to these as ‘small projects,’ but that may give the wrong
        impression. That term refers to anything that does not require a   For 2022 and beyond, SRNS is ramping up to an even higher level
        separate line item in the Congressional Budget, which means any   of small project performance. This calendar year, plans include
        project with a Total Estimated Cost less than $20 million. That includes   completion of construction for the MCC replacement, completion of
        some really substantial projects,” said Allen Neiling, SRNS Director,   construction for the MTF ventilation project, and replacement of four
        Savannah River Tritium Facility Projects. These represent many   more oxygen monitors.
        different ways in which SRNS is modernizing SRTE to keep it safely and   To avoid impacts to the SRTE production schedule, which the U.S.
        efficiently carrying out its national security missions.  Department of Defense relies upon, SRNS plans to take advantage of
        2021 was a banner year for SRTE’s “small” projects, with SRNS   a scheduled partial facility outage in 2025 to carry out six significant
        achieving several highly anticipated milestones and meeting objectives   maintenance and repair projects totaling nearly $100 million. These
        for spending. Those milestones included the installation and connection   projects support the Thermal Cycling Absorption Process
        of the new diesel generator. The diesel generator is part of the   (TCAP — the process SRTE uses to produce the highest-quality
        “bridging” strategy to maintain H Area Old Manufacturing (HAOM) until   tritium by isolating the pure tritium from other gases) and focus on
        the new Tritium Finishing Facility (one of SRNS’ large NNSA capital   replacing a portion of the system equipment, including the TCAP
        projects, now in design and planning), is completed and comes online   column and the hot-and-cold nitrogen system that allows the beds to
        to replace it. It provides emergency power to HAOM in the event site   function properly. SRNS has completed the conceptual designs and
        power is lost, to maintain the ventilation that prevents radiological   estimates for these six projects; initiation of final designs and long-
        release from the facility.                              lead procurements will begin in this year.
        The installation project installed the new diesel generator foundation,
        diesel generator and enclosure, fuel tank, and associated electrical
        commodities, including the switchgear. The connection project involved
        the tie-in of the electrical power from HAOM to the diesel generator
        to include installation of cable tray and supports, conduit, cable, and
        terminations. Two significant electrical outages to 234-H were required
        to tie in the electrical power to the diesel.
        “COVID-19 certainly impacted our schedule for completing the
        generator replacement,” Neiling said, “but in the end we were able to
        successfully complete the work and turn the new generator over to
        Operations ahead of the negotiated milestone extension.”

        Other projects that are part of the formal bridging strategy for HAOM
        will help enable the aging facility to continue safe operations. One of
        these is the replacement of four 60-year-old motor control centers
        (MCCs), which kicked off in 2021, mobilizing seven weeks ahead of
        the milestone due date. The fan control cabinet was fabricated and
        the four MCCs were received in 2021. Like several of the projects in
        SRTE, the transfers to the new MCCs have to be scheduled to take
        place during planned outages, so they can be accomplished without
        disrupting SRTE’s operations.
        A number of “small” projects serve to modernize other SRTE facilities.
        Among the most significant of these is the replacement of about
        30 outdated oxygen monitors in H Area New Manufacturing facility
        gloveboxes. In 2021, SRNS replaced five, the most ever done in
        a single year. Like the MCC work, this must be scheduled to be
        performed without impacting operations.
                                                                  A new exhaust stack erected as part of the multiphase project to provide new exhaust
        A large, multiphase project to provide new exhaust ventilation for   ventilation for the Savannah River Tritium Enterprise’s Materials Test Facility lab.
        SRTE’s Materials Test Facility (MTF) lab began in 2021. This project
   1   2   3   4   5   6   7   8   9   10